Actor availability is usually the hardest constraint in a shooting schedule, because unlike a location or a piece of equipment, an actor cannot be substituted. When an actor is only free for two weeks in November, those two weeks are fixed points and the rest of the schedule is built around them.
The practical work is threefold: collect availability accurately, place it before anything flexible, and compress each actor's days so you are paying for as few of them as possible.
Collecting availability properly
Most availability problems are information problems. The dates were vague, or they were given informally, or they changed and nobody updated the schedule.
Ask for specific dates in writing. Not "November is mostly fine". Actual unavailable dates, from their agent where there is one.
Ask what the unavailability is. There is a difference between a confirmed job, a possible job, a holiday, and a family commitment, and the flexibility varies enormously. Agents will usually tell you.
Ask about the whole span, not just the shoot. Rehearsal days, fittings, camera tests, and travel are all days the actor needs to be free.
Re-confirm before you lock. Availability given six weeks ago is not availability. Actors take other jobs, and a polite re-check before the schedule locks catches this while it is still cheap.
Record it somewhere the schedule can see. Availability living in an email thread is availability that will be violated. It belongs beside the schedule.
Where it goes in the process
Actor windows are fixed constraints, placed at step 4 of building a schedule, before any flexible material.
The order matters. If you build a schedule on location logic and then try to fit actors into it, you will rebuild it. If you place the immovable actor windows first and then group locations within them, you get there in fewer passes.
Where there are several constrained actors, place the most constrained first: the one with the narrowest window, or the one whose scenes are most numerous.
Compressing cast days
Once the hard windows are placed, the remaining work is efficiency: getting each actor's scenes into as few consecutive days as possible.
Read the day out of days and look for hold days. An actor working days 3, 4, 9 and 10 has four hold days in the middle. Moving one group of scenes so they work 3, 4, 5, 6 removes those four days from the budget and from the actor's commitment.
Two cautions.
Compression trades against location grouping. Grouping an actor's days tighter usually means splitting a location, and a location split costs a company move. Which is cheaper depends on the actor's rate and the size of the unit, and it is a real calculation rather than a rule.
Compression trades against performance. Putting all of an actor's material into four consecutive days means playing their entire arc in four days, sometimes out of order. For a lead with a substantial transformation, that can be a false economy.
The recurring nightmare: two leads, both with narrow availability, and the windows barely overlap. Every scene they share has to happen in the intersection, which might be four days for twenty pages of two-hander material. When this happens, the options are, in rough order of preference: shoot all their shared scenes in the overlap and everything else outside it, which usually works and makes those four days brutal; shoot one actor's coverage separately with a stand-in reading opposite, which is a real technique and produces noticeably worse work; or change the casting. Producers discover this at the point of offering a role to a second actor, which is why availability is checked before an offer, not after.
Handling conflicts
When the schedule and the availability genuinely do not fit, the options, roughly in order of how much they cost the film:
Move the shoot dates. Cheapest if you are early enough and nothing else is locked.
Reorder within the existing dates. Frequently possible and frequently overlooked. A schedule built around locations often has more flexibility than it appears.
Split the shoot. A block now, a block later, with the actor's availability in between. Expensive: two prep periods, two sets of location arrangements, continuity risk across the gap, and crew who may not be available for the second block. Sometimes it is genuinely the only option.
Shoot the actor's coverage separately. Their close-ups shot on their available days with someone reading opposite off camera. Legitimate and used more than people admit, and the results are usually detectably worse because actors are reacting to nothing.
Recast. The last resort, and occasionally the right answer. If an actor's availability makes a schedule impossible, that is real information about whether they can do the job.
Rewrite. Reduce the actor's scenes, or restructure so their material sits together. Cheap on the page, and worth considering before any of the expensive options above.
Day players and small parts
The scattered single days are a quieter version of the same problem.
An actor with one scene on day 22 costs a day, a travel arrangement, a fitting, and a slot in the second AD's morning. Where several day players are scattered across the schedule, grouping their scenes into shared days is a real saving in money and coordination.
The constraint is that day players' scenes are often tied to specific locations, so the grouping has to be done against the location plan rather than freely.
Children and restricted hours
A separate category with legal constraints on daily hours, weekly hours, and time of day, varying considerably by jurisdiction and by the child's age.
These are hard limits rather than preferences, and they have to be placed with the fixed constraints. Covered in working with child actors, animals, and weather.
On a short
The problem is usually worse on a short, not better, because you are frequently working with actors who have other jobs and are giving you weekends.
The practical approach:
Get availability before you cast, not after. Ask in the audition. An excellent actor who cannot make your dates is not an option, and finding out after you have offered is a bad conversation.
Get it in writing, with dates. A text message is fine. Vagueness is not.
Schedule the two-handers first. Wherever two actors share scenes, place those in the overlap of their availability and build everything else around it.
Confirm again a week before. People forget, or something comes up, and a week's notice is recoverable where a day's is not.
Have a plan for a no-show. On unpaid work it happens. Know which scenes you would shoot instead, which is the same discipline as building a contingency.
Once more than a handful of people have constraints, keeping this in a separate document stops working. Production management software exists largely to put availability in front of you while you are scheduling rather than after.
Next
The point in prep where the schedule stops being theoretical: walking the locations with every department and finding out what is really possible.
Get new posts by email
New posts and free templates by email. Unsubscribe in one click.
Availability against the schedule